Requirements Traceability Matrix
One table proving every requirement reached design, code and test — and that nothing untraceable was built.
The RTM answers two questions that nothing else answers cheaply: is every requirement covered by a test, and does every piece of built functionality trace back to a requirement? The second direction catches gold-plating and scope creep.
When to use it
- Regulated delivery (medical, financial, safety, public sector) where coverage evidence is mandatory.
- Fixed-price contracts, where acceptance depends on demonstrable coverage.
- Any project large enough that “did we test that?” cannot be answered from memory.
- Skip it for small internal product work where the Test Plan already references stories directly.
What it must answer
- For each business requirement: which system requirement implements it, which design element realises it, which tests verify it, and what the current result is.
- For each test: which requirement justifies its existence.
- What is deliberately untested, and who accepted that.
Template
# Requirements Traceability Matrix: <Project>
| Field | Value |
|---|---|
| Version / date | |
| Maintained by | |
| Sources | BRD v_, SRS v_, Test Plan v_ |
## Forward trace
| BR ID | SRS ID | Design ref | Code ref | Test case IDs | Test result | Status |
|---|---|---|---|---|---|---|
## Backward trace (orphans)
| Built element | Traces to | Justification if none |
|---|---|---|
## Coverage summary
| Priority | Requirements | With >=1 test | Passed | Deferred |
|---|---|---|---|---|
## Accepted gaps
| Requirement | Gap | Accepted by | Date | Compensating control |
|---|---|---|---|---|
Worked example
# Requirements Traceability Matrix: Access Provisioning Service
Version 3 / 2026-11-04. Maintained by H. Ito.
Sources: BRD v1.2, SRS v2.0, Test Plan v2.
## Forward trace
| BR ID | SRS ID | Design ref | Code ref | Test case IDs | Result | Status |
|---|---|---|---|---|---|---|
| BR-01 | FR-01 | SAD §4.2 event ingest | ingest/handler.go | TC-101, TC-102, TC-118 | Pass | Verified |
| BR-01 | FR-02 | SAD §4.3 bundle resolver | bundles/resolve.go | TC-110, TC-111 | Pass | Verified |
| BR-02 | FR-03 | TDD §3 approval state machine | approval/*.go | TC-120…TC-127 | Pass | Verified |
| BR-02 | FR-05 | SAD §6 audit sink | audit/writer.go | TC-140, TC-141, TC-142 | Pass | Verified |
| BR-03 | FR-04 | TDD §5 leaver scheduler | leaver/schedule.go | TC-150, TC-151 | 1 fail (TC-151, legacy ERP nightly only) | Gap accepted |
| BR-04 | FR-06 | SAD §4.4 bundle admin UI | admin/ | TC-160, TC-161 | Pass | Verified |
| BR-05 | — | — | — | — | — | Deferred to phase 2 |
| — | NFR-01 | SAD §7 | — | TC-200 (load) | Pass — p95 = 11 min vs 30 target | Verified |
| — | NFR-03 | SAD §7 | — | TC-210 (chaos) | Pass | Verified |
| — | NFR-04 | Runbook §9 | — | DR-01 (exercise 2026-10-22) | Pass — RTO 2h51m | Verified |
| — | NFR-06 | Data inventory v4 | — | TC-230 (retention) | Pass | Verified |
## Backward trace (orphans)
| Built element | Traces to | Justification if none |
|---|---|---|
| /admin/bulk-import | — | Built for the September intake load; no requirement. Retained — approved by K. Ferreira 2026-09-08, documented as FR-08 in SRS v2.1 |
| Slack notification channel | — | Removed before release. No requirement, no owner |
## Coverage summary
| Priority | Requirements | With >=1 test | Passed | Deferred |
|---|---|---|---|---|
| Must | 12 | 12 | 11 | 0 |
| Should | 3 | 3 | 3 | 0 |
| Could | 2 | 0 | 0 | 2 |
## Accepted gaps
| Requirement | Gap | Accepted by | Date | Compensating control |
|---|---|---|---|---|
| BR-03 / FR-04 | Legacy ERP revokes on the nightly batch, so worst case is 26h not 1h | L. Haddad (Internal Audit), K. Ferreira | 2026-10-30 | Daily exception report of accounts active past their leave date, reviewed by People Ops; ERP replacement on the FY2027 roadmap |
Common mistakes
- Only the forward trace. Without the backward trace you never discover the feature nobody asked for — which still has to be maintained and secured.
- Maintained by hand at the end. An RTM written the week before acceptance is a fiction. Generate it from IDs already present in commits and test names.
- Test IDs with no results. Coverage means a test that ran and passed, not a test that exists.
- Gaps hidden as “partially verified”. Name the gap, name who accepted it, name the compensating control. That row is the most valuable one in the document.
- Requirement IDs that change. Once published, an ID is permanent; supersede rather than renumber, or every trace breaks.
Related templates
- Business Requirements Document — the BR column.
- Software Requirements Specification — the SRS column.
- Test Plan — defines what “verified” means here.
- Test Summary Report — the results column comes from there.
- Requirements & Analysis — the other four requirements templates.
Linked from
- Business Requirements Document — What the business needs and why, stated without prescribing a solution.
- Software Requirements Specification — System-level functional and non-functional requirements, each one testable.
- Test Plan — What will be tested, how, by whom, and what we are consciously not testing.
- Test Summary Report — What was tested, what was found, and what is being shipped with known problems.