An SRS states what the system must do, precisely enough that two independent teams would build something equivalent and a tester could write cases without asking questions. It is the bridge between the business intent in a BRD and the design in an architecture document.

When to use it

  • For systems built under contract, or where a formal acceptance gate exists.
  • In regulated environments where evidence of specification is required.
  • For anything with meaningful non-functional demands — throughput, latency, retention, availability.
  • A backlog of user stories can replace an SRS for product work with a stable team; it cannot replace one for a fixed-price contract.

What it must answer

  • What does the system do, for whom, under what conditions?
  • What are the measurable quality attributes, with numbers and measurement points?
  • What are the interfaces, and who owns each side of them?
  • What is explicitly excluded?

Template

  # Software Requirements Specification: <System>

| Field | Value |
|---|---|
| Version / date | |
| Author / owner | |
| Status | |
| Supersedes | |

## 1. Purpose and scope
## 2. Definitions and abbreviations
## 3. System context
Actors, external systems, trust boundaries. One diagram.

## 4. Functional requirements
| ID | Requirement | Priority | Source | Verification |
|---|---|---|---|---|

Write each as: "The system shall <observable behaviour> when <condition>."
Verification is one of: test, demonstration, inspection, analysis.

## 5. Non-functional requirements
| ID | Attribute | Requirement | Measured at | Verification |
|---|---|---|---|---|

Cover at least: performance, capacity, availability, recovery, security,
privacy/retention, accessibility, observability, portability.

## 6. External interfaces
| Interface | Direction | Protocol / format | Owner | Failure behaviour |
|---|---|---|---|---|

## 7. Data requirements
Entities, retention, residency, classification.

## 8. Constraints
## 9. Out of scope
## 10. Open issues
| # | Question | Owner | Needed by |
|---|---|---|---|
  

Worked example

  # Software Requirements Specification: Access Provisioning Service

| Field | Value |
|---|---|
| Version / date | 2.0 / 2026-06-30 |
| Owner | A. Vogel |
| Status | Approved for build |

## 3. System context
Actors: HR system (source of record), line manager (approver), target systems
(11), service desk agent (exception handling), auditor (read-only). The service
is inside the corporate trust boundary; target system credentials live in the
existing secrets manager.

## 4. Functional requirements
| ID | Requirement | Priority | Source | Verification |
|---|---|---|---|---|
| FR-01 | The system shall create a provisioning request within 5 minutes of a new employee record appearing in the HR feed | Must | BR-01 | Test |
| FR-02 | The system shall resolve the employee's job code to an access bundle, and shall reject the request if no bundle matches | Must | BR-01 | Test |
| FR-03 | The system shall require line-manager approval for any entitlement not present in the resolved bundle | Must | BR-02 | Test |
| FR-04 | The system shall revoke all entitlements within 1 hour of the recorded leave date passing | Must | BR-03 | Test |
| FR-05 | The system shall record, for every grant and revocation, the actor, timestamp, entitlement and justification, in an append-only log | Must | BR-02, audit | Inspection |
| FR-06 | The system shall allow a People Ops administrator to modify bundle contents without a code deployment | Should | BR-04 | Demonstration |
| FR-07 | The system shall retry a failed target-system call 5 times with exponential backoff before raising a service desk ticket | Must | Ops | Test |

## 5. Non-functional requirements
| ID | Attribute | Requirement | Measured at | Verification |
|---|---|---|---|---|
| NFR-01 | Performance | 95th percentile end-to-end provisioning completes within 30 minutes of the HR event | Service metrics, weekly | Test |
| NFR-02 | Capacity | Sustains 40 joiner events per hour and a bulk load of 500 events (annual graduate intake) | Load test | Test |
| NFR-03 | Availability | 99.5% monthly, business hours; degraded mode may queue events for up to 4 hours | Synthetic probe | Analysis |
| NFR-04 | Recovery | RPO 15 minutes, RTO 4 hours | DR exercise | Demonstration |
| NFR-05 | Security | No entitlement change may be made by the service without a corresponding approved request; service credentials rotate every 90 days | Pen test, secrets audit | Test |
| NFR-06 | Privacy | Personal data limited to name, employee ID, job code, dates; audit log retained 7 years, operational logs 90 days | Data inventory | Inspection |
| NFR-07 | Observability | Every request exposes a correlation ID present in all downstream calls and in the audit log | Log sampling | Inspection |

## 6. External interfaces
| Interface | Direction | Protocol / format | Owner | Failure behaviour |
|---|---|---|---|---|
| HR feed | In | Webhook, JSON, at-least-once | HR platform team | Deduplicate on event ID; alert if no event in 24h |
| Target systems (9) | Out | SCIM 2.0 | Identity platform | Retry per FR-07, then ticket |
| Legacy ERP | Out | SFTP batch, fixed-width, nightly | ERP team | File rejected -> ticket + no partial apply |
| Audit export | Out | Signed NDJSON to object storage, daily | Internal Audit | Missing file alerts within 2h |

## 9. Out of scope
Contractor identities, badge provisioning, payroll enrolment, mobile device
enrolment.

## 10. Open issues
| # | Question | Owner | Needed by |
|---|---|---|---|
| 1 | Does the legacy ERP support same-day revocation, or only nightly? | ERP team | 2026-07-15 — affects FR-04 |
  

Common mistakes

  • Unverifiable requirements. “The system shall be user-friendly” cannot be tested, so it will not be. If you cannot name a verification method, it is not a requirement.
  • Non-functional requirements without a measurement point. “99.9% available” measured where — the load balancer, or the user’s browser? The difference is often an order of magnitude of work.
  • Mixing design into the specification. “The system shall store requests in PostgreSQL” belongs in the Technical Design Document unless the database is genuinely a contractual constraint.
  • No source column. Without traceability back to a business requirement, nobody can tell which requirements can be cut.
  • Open issues hidden in prose. An explicit open-issues table with dates is what keeps a specification honest during review.