Test Summary Report
What was tested, what was found, and what is being shipped with known problems.
Last updated
The test summary report is the evidence behind a release decision. It is not a recommendation to ship — that decision belongs to the business owner. Keeping those separate is what lets a tester state uncomfortable facts without appearing to block the release.
When to use it
- At the end of every formal test cycle, before a go/no-go decision.
- As the retained evidence for audit and for contractual acceptance.
- As the input to the release decision meeting, circulated beforehand.
What it must answer
- Was the plan executed, and where did execution deviate from it?
- What are the results against the stated exit criteria?
- What is still open, and what is the risk of shipping with it open?
- What could we not test, and what does that leave unknown?
Template
Test Summary Report: <Release>
| Field | Value |
|---|---|
| Cycle / dates | |
| Test lead | |
| Build tested | commit / version |
| Related | Test Plan v_, RTM v_ |
1. Summary
Three sentences: what was tested, headline result, what remains open.
2. Execution
| Suite | Planned | Executed | Passed | Failed | Blocked | Not run |
|---|
Explain every deviation from plan.
3. Exit criteria status
| Criterion | Target | Actual | Met? |
|---|
4. Defects
| Severity | Found | Fixed | Open | Deferred |
|---|
Open defects listed individually with impact and workaround.
5. Coverage
By requirement priority; reference the RTM.
6. Non-functional results
Performance, resilience, security, accessibility — numbers, not verdicts.
7. Untested areas and residual risk
| Area | Why not tested | Residual risk | Accepted by |
|---|
8. Environment and data notes
Anything that limits confidence in the results.
9. Conclusion
State the facts against the criteria. The release decision belongs to the
business owner and is recorded separately.
# Test Summary Report: <Release>
| Field | Value |
|---|---|
| Cycle / dates | |
| Test lead | |
| Build tested | commit / version |
| Related | Test Plan v_, RTM v_ |
## 1. Summary
Three sentences: what was tested, headline result, what remains open.
## 2. Execution
| Suite | Planned | Executed | Passed | Failed | Blocked | Not run |
|---|---|---|---|---|---|---|
Explain every deviation from plan.
## 3. Exit criteria status
| Criterion | Target | Actual | Met? |
|---|---|---|---|
## 4. Defects
| Severity | Found | Fixed | Open | Deferred |
|---|---|---|---|---|
Open defects listed individually with impact and workaround.
## 5. Coverage
By requirement priority; reference the RTM.
## 6. Non-functional results
Performance, resilience, security, accessibility — numbers, not verdicts.
## 7. Untested areas and residual risk
| Area | Why not tested | Residual risk | Accepted by |
|---|---|---|---|
## 8. Environment and data notes
Anything that limits confidence in the results.
## 9. Conclusion
State the facts against the criteria. The release decision belongs to the
business owner and is recorded separately.
Worked example
Test Summary Report: Access Provisioning Service 1.0
| Field | Value |
|---|---|
| Cycle / dates | System test 2026-10-05 to 2026-11-14; UAT 2026-11-17 to 2026-11-28 |
| Test lead | H. Ito |
| Build tested | v1.0.0-rc4, commit 9f3c1ab |
1. Summary
All Must requirements are covered and passing except FR-04 for the legacy ERP,
where revocation is nightly rather than hourly. One Sev-1 defect was found late
(DEF-2026-0311) and fixed. Two Sev-3 defects remain open with workarounds, and
one accepted gap is carried into production with a compensating control.
2. Execution
| Suite | Planned | Executed | Passed | Failed | Blocked | Not run |
|---|---|---|---|---|---|---|
| Integration | 186 | 186 | 184 | 2 | 0 | 0 |
| Contract | 44 | 44 | 44 | 0 | 0 | 0 |
| Performance | 9 | 9 | 9 | 0 | 0 | 0 |
| Security (pen test) | — | 1 engagement | — | — | — | — |
| DR exercise | 1 | 1 | 1 | 0 | 0 | 0 |
| UAT scenarios | 8 | 8 | 7 | 1 | 0 | 0 |
Deviation: integration testing was suspended 2026-10-21 to 2026-10-23 when the
vendor sandbox changed its 3DS response shape without notice. The affected 26
cases were re-run from a clean state after contract recordings were refreshed.
3. Exit criteria status
| Criterion | Target | Actual | Met? |
|---|---|---|---|
| Must requirements with a passing test | 100% | 11 of 12 | No — see accepted gap |
| Should requirements passing | >= 95% | 100% (3 of 3) | Yes |
| Open Sev-1 | 0 | 0 | Yes |
| Open Sev-2 without approved deferral | 0 | 0 | Yes |
| p95 provisioning latency at 40 events/h | <= 30 min | 11 min | Yes |
| 500-event intake within one working day | Yes | 3h 12m | Yes |
| DR: RTO / RPO | 4h / 15 min | 2h 51m / 4 min | Yes |
| Pen test High/Critical unresolved | 0 | 0 (2 Medium open, scheduled) | Yes |
| Audit log completeness on 1,000-grant sample | 100% | 100% | Yes |
4. Defects
| Severity | Found | Fixed | Open | Deferred |
|---|---|---|---|---|
| Sev-1 | 1 | 1 | 0 | 0 |
| Sev-2 | 6 | 6 | 0 | 0 |
| Sev-3 | 19 | 17 | 2 | 0 |
| Sev-4 | 31 | 12 | 19 | 19 |
Open Sev-3:
- DEF-2026-0327: bundle admin screen paginates incorrectly beyond 200 bundles.
Impact: People Ops cannot see bundles past page 4. Workaround: search by job
code. Fix scheduled 1.0.1. - DEF-2026-0333: the daily exception report lists leavers in a non-obvious
order. Impact: cosmetic but slows the review. Workaround: sort in the
spreadsheet. Fix scheduled 1.0.1.
5. Coverage
Per the RTM at v3:
| Priority | Requirements | With >=1 test | Passing | Notes |
|---|---|---|---|---|
| Must | 12 | 12 (100%) | 11 | FR-04 fails only for the legacy ERP target |
| Should | 3 | 3 (100%) | 3 | — |
| Could | 2 | 0 | 0 | Deferred to phase 2, agreed with the business owner |
| NFR | 7 | 7 (100%) | 7 | Includes the DR exercise and the pen test |
Backward trace found two built elements with no requirement: /admin/bulk-import,
retained and written up as FR-08 in SRS v2.1, and a Slack notification channel,
removed before the release. No other untraceable functionality was found.
6. Non-functional results
- Performance: p95 11 min, p99 19 min at 40 events/hour. Bottleneck is adapter
latency, not the service. - Resilience: with one adapter fully down, other entitlements continued to
apply; requests ended PARTIAL with tickets raised, as designed. - Security: pen test found 2 Medium (verbose error message on the admin login;
missingCache-Control: no-storeon an authenticated response). Both fixed
in rc4 and retested; no High or Critical. - Accessibility: admin UI at WCAG 2.1 AA except two contrast failures on the
status badges — DEF-2026-0339, fix scheduled 1.0.1.
7. Untested areas and residual risk
| Area | Why not tested | Residual risk | Accepted by |
|---|---|---|---|
| Contractor identities | Not built | None for this release | K. Ferreira |
| Sustained load beyond 500 events/day | No business case for higher volumes | Unknown behaviour above ~2x peak; would need a load test before any acquisition-driven intake | A. Vogel |
| ERP behaviour under simultaneous joiner and leaver for the same person | Cannot be produced in the vendor sandbox | Ordering ambiguity in a rare case; mitigated by the daily exception report | A. Vogel, L. Haddad |
8. Environment and data notes
UAT ran on anonymised production data refreshed 2026-11-14. Two UAT scenarios
used manually constructed records because the anonymised set contained no
employee without a manager — the very case that scenario 2 needed. That case is
therefore less well evidenced than the others.
9. Conclusion
Exit criteria are met except “100% of Must requirements passing”, which stands
at 11 of 12 due to the legacy ERP nightly revocation window (FR-04). That gap
is documented in the RTM with a compensating control accepted by Internal Audit
and the business owner. All other criteria are met with margin.
# Test Summary Report: Access Provisioning Service 1.0
| Field | Value |
|---|---|
| Cycle / dates | System test 2026-10-05 to 2026-11-14; UAT 2026-11-17 to 2026-11-28 |
| Test lead | H. Ito |
| Build tested | v1.0.0-rc4, commit 9f3c1ab |
## 1. Summary
All Must requirements are covered and passing except FR-04 for the legacy ERP,
where revocation is nightly rather than hourly. One Sev-1 defect was found late
(DEF-2026-0311) and fixed. Two Sev-3 defects remain open with workarounds, and
one accepted gap is carried into production with a compensating control.
## 2. Execution
| Suite | Planned | Executed | Passed | Failed | Blocked | Not run |
|---|---|---|---|---|---|---|
| Integration | 186 | 186 | 184 | 2 | 0 | 0 |
| Contract | 44 | 44 | 44 | 0 | 0 | 0 |
| Performance | 9 | 9 | 9 | 0 | 0 | 0 |
| Security (pen test) | — | 1 engagement | — | — | — | — |
| DR exercise | 1 | 1 | 1 | 0 | 0 | 0 |
| UAT scenarios | 8 | 8 | 7 | 1 | 0 | 0 |
Deviation: integration testing was suspended 2026-10-21 to 2026-10-23 when the
vendor sandbox changed its 3DS response shape without notice. The affected 26
cases were re-run from a clean state after contract recordings were refreshed.
## 3. Exit criteria status
| Criterion | Target | Actual | Met? |
|---|---|---|---|
| Must requirements with a passing test | 100% | 11 of 12 | No — see accepted gap |
| Should requirements passing | >= 95% | 100% (3 of 3) | Yes |
| Open Sev-1 | 0 | 0 | Yes |
| Open Sev-2 without approved deferral | 0 | 0 | Yes |
| p95 provisioning latency at 40 events/h | <= 30 min | 11 min | Yes |
| 500-event intake within one working day | Yes | 3h 12m | Yes |
| DR: RTO / RPO | 4h / 15 min | 2h 51m / 4 min | Yes |
| Pen test High/Critical unresolved | 0 | 0 (2 Medium open, scheduled) | Yes |
| Audit log completeness on 1,000-grant sample | 100% | 100% | Yes |
## 4. Defects
| Severity | Found | Fixed | Open | Deferred |
|---|---|---|---|---|
| Sev-1 | 1 | 1 | 0 | 0 |
| Sev-2 | 6 | 6 | 0 | 0 |
| Sev-3 | 19 | 17 | 2 | 0 |
| Sev-4 | 31 | 12 | 19 | 19 |
Open Sev-3:
- DEF-2026-0327: bundle admin screen paginates incorrectly beyond 200 bundles.
Impact: People Ops cannot see bundles past page 4. Workaround: search by job
code. Fix scheduled 1.0.1.
- DEF-2026-0333: the daily exception report lists leavers in a non-obvious
order. Impact: cosmetic but slows the review. Workaround: sort in the
spreadsheet. Fix scheduled 1.0.1.
## 5. Coverage
Per the RTM at v3:
| Priority | Requirements | With >=1 test | Passing | Notes |
|---|---|---|---|---|
| Must | 12 | 12 (100%) | 11 | FR-04 fails only for the legacy ERP target |
| Should | 3 | 3 (100%) | 3 | — |
| Could | 2 | 0 | 0 | Deferred to phase 2, agreed with the business owner |
| NFR | 7 | 7 (100%) | 7 | Includes the DR exercise and the pen test |
Backward trace found two built elements with no requirement: `/admin/bulk-import`,
retained and written up as FR-08 in SRS v2.1, and a Slack notification channel,
removed before the release. No other untraceable functionality was found.
## 6. Non-functional results
- Performance: p95 11 min, p99 19 min at 40 events/hour. Bottleneck is adapter
latency, not the service.
- Resilience: with one adapter fully down, other entitlements continued to
apply; requests ended PARTIAL with tickets raised, as designed.
- Security: pen test found 2 Medium (verbose error message on the admin login;
missing `Cache-Control: no-store` on an authenticated response). Both fixed
in rc4 and retested; no High or Critical.
- Accessibility: admin UI at WCAG 2.1 AA except two contrast failures on the
status badges — DEF-2026-0339, fix scheduled 1.0.1.
## 7. Untested areas and residual risk
| Area | Why not tested | Residual risk | Accepted by |
|---|---|---|---|
| Contractor identities | Not built | None for this release | K. Ferreira |
| Sustained load beyond 500 events/day | No business case for higher volumes | Unknown behaviour above ~2x peak; would need a load test before any acquisition-driven intake | A. Vogel |
| ERP behaviour under simultaneous joiner and leaver for the same person | Cannot be produced in the vendor sandbox | Ordering ambiguity in a rare case; mitigated by the daily exception report | A. Vogel, L. Haddad |
## 8. Environment and data notes
UAT ran on anonymised production data refreshed 2026-11-14. Two UAT scenarios
used manually constructed records because the anonymised set contained no
employee without a manager — the very case that scenario 2 needed. That case is
therefore less well evidenced than the others.
## 9. Conclusion
Exit criteria are met except "100% of Must requirements passing", which stands
at 11 of 12 due to the legacy ERP nightly revocation window (FR-04). That gap
is documented in the RTM with a compensating control accepted by Internal Audit
and the business owner. All other criteria are met with margin.
Common mistakes
- A recommendation instead of evidence. “QA recommends release” transfers a business decision to the wrong person and discourages honest reporting.
- Pass rates without the denominator’s story. 184 of 186 looks fine until you learn 26 cases were re-run after a mid-cycle environment change.
- No untested-areas section. What was not tested is the part a release decision most needs and least often gets.
- Open defects summarised only as counts. List them individually with impact and workaround; a count tells the reader nothing about risk.
- Written after the go-live decision. Then it is a record of a decision, not an input to one.
Related templates
- Test Plan — the criteria reported against here.
- UAT Plan — the acceptance side of the evidence.
- Requirements Traceability Matrix — the coverage source.
- Release Notes — where open defects become known issues.
- Testing & QA — the other four testing and QA templates.
Linked from
- Requirements Traceability Matrix — One table proving every requirement reached design, code and test — and that nothing untraceable was built.
- Test Plan — What will be tested, how, by whom, and what we are consciously not testing.