On this page
summarize
Status Report
A weekly one-pager that reports the delta, the decisions needed, and the truth about the date.
Most status reports are written to reassure. A useful one is written to surface the two or three things a reader can act on, and to report schedule confidence honestly enough that bad news arrives early rather than at the deadline.
When to use it
- On a fixed weekly or fortnightly cadence for any project with a sponsor.
- Ad hoc when a milestone date changes — do not wait for the next scheduled report.
What it must answer
- Is the end date still credible, and has that answer changed since last time?
- What did we finish, and what did we say we would finish and did not?
- What decision or unblocking do I need from the reader, by when?
Template
# Status Report: <Project> — week ending YYYY-MM-DD
**Overall:** Green / Amber / Red (last period: X)
**Next milestone:** <name>, due YYYY-MM-DD, confidence High / Medium / Low
## Decisions needed
| # | Decision | Owner | Needed by | Impact if late |
|---|---|---|---|---|
## Progress this period
- Completed: ...
- Slipped: ... (planned <date>, now <date>, cause)
## Plan for next period
- ...
## Risks and issues (changes only)
| ID | Item | Change since last report |
|---|---|---|
## Metrics
| Metric | Last | Now | Target |
|---|---|---|---|
## Budget
Spent to date / forecast at completion / approved.
Worked example
# Status Report: Payment Gateway Migration — week ending 2026-08-21
**Overall:** Amber (last period: Green)
**Next milestone:** M3 — 5% live traffic, due 2026-09-30, confidence Medium
## Decisions needed
| # | Decision | Owner | Needed by | Impact if late |
|---|---|---|---|---|
| 1 | Confirm P. Nowak stays at 50% through September | M. Duarte | 2026-08-28 | Reconciliation feed slips 3 weeks and consumes all float |
| 2 | Accept 3DS challenge rate rising to 8% during ramp | R. Okafor | 2026-09-04 | Ramp cannot start; M3 slips |
## Progress this period
- Completed: sandbox test suite green on 5 consecutive nightly runs — M2 met,
one week late.
- Completed: routing flag service deployed to production, disabled.
- Slipped: reconciliation feed UAT (planned 2026-08-19, now 2026-09-02).
Cause: Finance systems team unavailable during month-end close. Known
dependency, not a new one.
## Plan for next period
- Dry-run the ramp procedure against 0% traffic in production.
- Reconciliation feed UAT with Finance, 2026-09-01.
- Close out the PCI scope review with Security.
## Risks and issues (changes only)
| ID | Item | Change since last report |
|---|---|---|
| R-04 | Auth rate drop after cutover | Unchanged. Mitigation (automatic rollback below 95.5%) implemented this week. |
| R-07 | Shared data engineer | Escalated to Amber — this is decision 1 above. |
| I-02 | Sandbox rate limits | Closed. Provider raised the limit on 2026-08-18. |
## Metrics
| Metric | Last | Now | Target |
|---|---|---|---|
| Sandbox suite pass rate | 92% | 100% | 100% |
| Live volume on new provider | 0% | 0% | 5% by 2026-09-30 |
| Open defects (sev 1–2) | 3 | 1 | 0 before ramp |
## Budget
Spent EUR 402k of EUR 785k approved. Forecast at completion EUR 760k,
including EUR 45k of the EUR 100k contingency. No new budget request.
Common mistakes
- Green until the week it is Red. A status that never goes Amber is not being measured; it is being performed. State milestone confidence separately from overall status so the trend is visible.
- A list of activity instead of outcomes. “Held three workshops” is not progress. “Integration spec signed by Finance” is.
- Decisions buried in prose. Put them in a table at the top with a date. A decision needed “soon” will not be made.
- Restating the whole risk register every week. Report the changes; the full list lives in the RAID Log.
- Silent re-baselining. If the milestone date moved, say the old date, the new date, and the cause in the same line.
Related templates
- Project Plan — the baseline this reports against.
- RAID Log — the source of the risks and issues section.
- Meeting Minutes — where decisions get recorded once made.
- Project Management — the other four project-management templates.
Linked from
- Meeting Minutes — Decisions and actions, captured in a form that survives the disagreement three months later.
- Project Charter — The one-page authorisation that says a project exists, who runs it, and what 'done' means.
- Project Plan — Schedule, dependencies, resourcing and the critical path, in a form a delivery team will actually maintain.
- RAID Log — One table for Risks, Assumptions, Issues and Dependencies — the project's short-term memory.
Last updated 23 Aug 2026, 00:00 UTC.